Related Documents

Summary

2017/3847/P
385

Application Documents

The links below are to PDF files. To view PDFs you need to download and install Adobe Acrobat Reader onto your computer. Help for people with visual disabilities: The files contained scanned documents that cannot be read by screen readers. If this is a problem for you please use the Planning online support form to request an alternative format.


Drawings can be large files. The quality of the image depends on the quality of the original submission.


Date Created Title Document Type
02/02/2024 17:00:09 Extension to working hours form - CMP SM Suite - Final v2 Other
07/02/2023 11:01:46 Construction Management Plan (CMP)- updated phase 2B Other
08/11/2022 11:51:23 Bus Infrastructure Safeguarding Plan First Schedule, Part 3, Clause 38.1 – Phase 2B and 3 Other
08/11/2022 11:21:06 Construction Management Plan (CMP) - Phase 2B (Version 4) Other
19/04/2021 12:52:51 CMP- Construction Management Plan Other
16/09/2020 10:43:42 Construction Management Plan Phase 1 for PFS site only Other
26/06/2018 14:18:09 Legal agreement Legal Agreement
18/06/2018 09:38:17 Camden Goods Yard - Final Decision Notice 2017 3847 P Decision Notice
21/12/2017 15:23:12 89x Responses (Redacted) Consultation Response
29/11/2017 16:52:18 1 x response (Redacted) Consultation Response
28/11/2017 16:07:22 1x response (Redacted) Consultation Response
23/11/2017 13:42:09 1 x response Consultation Response
16/11/2017 13:54:08 Env Health Noise Obs Camden Goods Yard Other
16/11/2017 09:55:47 Daylight & Sunlight Review Report by Delva Patman Redler - November 2017 Supporting Documents
15/11/2017 21:01:31 CGY Committee Report (optimised for print) VERY Large File Other
15/11/2017 20:52:28 CGY Committee Report (complete) optimised for screen LARGE FILE Other
15/11/2017 20:20:58 CGY Committee Report (Text only) Other
15/11/2017 10:19:35 A9 BIA Addendum GY Basement Wall southwest bdy_SLS 301017 Revised Drawing
15/11/2017 10:19:23 Applicants response re AQ : ENER-G 150 (Low NOx) CHP- Technical Datasheet Revised Drawing
15/11/2017 10:19:08 Applicants Response to CGY Planning Framework 03 11 17 Revised Drawing
15/11/2017 10:18:54 Applicants notes on Bus Delays Revised Drawing
15/11/2017 10:18:27 160630-006B Highway Layout Revised Drawing
15/11/2017 10:18:19 A9 BIA addendum GY Dbl Hght Basement Wall 301017 Revised Drawing
15/11/2017 10:17:37 C DAS Ch6 Design Statement Block D addendum Revised Drawing
15/11/2017 10:17:23 C DAS Ch6 Design Statement Block C addendum LARGE FILE Revised Drawing
15/11/2017 10:17:03 C DAS Ch6 Design Statement Block B addendum VERY LARGE FILE Revised Drawing
15/11/2017 10:16:45 C DAS Ch6 Design Statement Block A addendum Revised Drawing
15/11/2017 10:16:35 C DAS Ch6 Design Statement Block PFS addendum Revised Drawing
15/11/2017 10:16:23 C DAS Ch6 Design Statement Block F addendum Revised Drawing
15/11/2017 10:16:14 C DAS Ch6 Design Statement Block E2 addendum Revised Drawing
15/11/2017 10:16:03 C DAS Ch6 Design Statement Block E1 addendum Revised Drawing
13/11/2017 14:18:36 Newlon Housing Trust Response (reconsult) Consultation Response
13/11/2017 08:28:16 1 x Response 8 (Re-consult) Consultation Response
13/11/2017 08:25:34 1 x Response (Redacted) Consultation Response
09/11/2017 15:56:44 1 x Response - Cllr Cotton Consultation Response
05/03/2018 09:47:15 Main site & PFS Site 1095_00_07_022 (Rev P1) Supporting Documents
08/11/2017 21:04:34 A9 Basement Impact Assessment 2017_Version 05 Revised Drawing
08/11/2017 20:43:50 Campbell Reith BIA Audit report [ASPemb12466-88 -081117 Camden Goods Yard - F1] Correspondence
08/11/2017 08:30:33 1 x Response (Markettech) (Redacted) Consultation Response
07/11/2017 15:10:32 1 x Response - Thames Water Consultation Response
06/11/2017 13:21:32 1 x Response - GYTA Consultation Response
06/11/2017 12:55:19 1 x Response (Redacted) Consultation Response
02/11/2017 12:14:22 Canal & River Trust Response (reconsult) (Redacted) Consultation Response
31/10/2017 15:40:05 Response 7 (reconsult) (Redacted) Consultation Response
31/10/2017 15:38:39 GLAAS response (reconsult) Consultation Response
30/10/2017 22:32:06 Primrose Hill CAAC response (reconsult) (Redacted) Consultation Response
30/10/2017 22:30:11 Responses 4-6 (reconsult) (Redacted) Consultation Response
30/10/2017 22:28:24 HS2 Response (reconsult) (Redacted) Consultation Response
30/10/2017 22:26:03 Natural England (reconsult) (Redacted) Consultation Response
26/10/2017 14:34:14 Response 3 (reconsult) (Redacted) Consultation Response
25/10/2017 14:29:47 Response 2 (reconsult) (Redacted) Consultation Response
25/10/2017 14:26:07 Response 1 (reconsult) (Redacted) Consultation Response
24/10/2017 11:12:58 Markettech Response (Redacted) Consultation Response
24/10/2017 11:12:29 NATIONAL_GRID_Response Consultation Response
20/10/2017 10:18:55 Historic England response (Redacted) Consultation Response
19/10/2017 11:51:49 BE1 Block E1 Bay drawings_Rev A Revised Drawing
19/10/2017 11:51:03 BA Block A Bay drawings_Rev A Revised Drawing
18/10/2017 16:56:33 LBC initial design and landscape comments Correspondence
18/10/2017 10:05:06 Met Police Reconsult Response Consultation Response
13/10/2017 10:11:31 Environmental Implications Letter LUK11-23069_1 Supporting Documents
12/10/2017 18:03:49 BL Landscape revised Tree Planting Plan P10606-00-001-104 Revised Drawing
12/10/2017 18:03:42 BL Landscape revised Hardworks plan P10606-00-001-102 Revised Drawing
12/10/2017 18:03:34 BL Landscape revised Softworks plan P10606-00-001-103 Revised Drawing
12/10/2017 18:02:52 BL Landscape typical tree details P10606-00-001-810 Revised Drawing
12/10/2017 17:08:56 Building for Life assessment for Camden Goods Yard Supporting Documents
12/10/2017 16:52:56 Response 105 (Redacted) Consultation Response
12/10/2017 16:52:37 Response 104 (Redacted) Consultation Response
12/10/2017 16:52:09 Response 103 (Redacted) Consultation Response
12/10/2017 16:51:53 Response 102 (Redacted) Consultation Response
12/10/2017 16:51:29 Response 101 (Redacted) Consultation Response
12/10/2017 16:51:09 Response 100 (Redacted) Consultation Response
12/10/2017 16:50:51 Response 99 (Redacted) Consultation Response
12/10/2017 16:50:33 Response 98 (Redacted) Consultation Response
12/10/2017 16:50:17 Response 97 (Redacted) Consultation Response
12/10/2017 16:49:52 Response 90 to 96 (Redacted) Consultation Response
12/10/2017 16:48:52 Response 88 (Redacted) Consultation Response
12/10/2017 14:56:10 Camden Railway Heritage Trust Response 89 Consultation Response
12/10/2017 11:48:56 Camden issued request for revisions clarifications Correspondence
12/10/2017 11:46:23 BBS Response to GLA-LBC Accessibility Comments 18-09-17 provisional Revised Drawing
12/10/2017 11:45:38 D4 ES Vol 3A Tech 10.1 Revised ADF Levels 100A Chalk Farm Road Revised Drawing
12/10/2017 11:39:08 A20 Statement of Community Involvement Revised Revised Drawing
12/10/2017 11:36:17 A13 Framework Travel Plan Revised extracted from slh23160 - CGY - TP Addendum FINAL Revised Drawing
12/10/2017 11:33:10 Revisions cover Letter - draft - CGY amendments and clarifications - 12 10 2017 Revised Drawing
12/10/2017 11:33:01 BL Landscape Revised Tree Retention strategy 105 Revised Drawing
12/10/2017 11:32:51 BL Landscape typical tree details P10606-00-001-810 Revised Drawing
12/10/2017 11:32:41 A9 Basement Impact Assessment Groundwater Characteristics D4 ES Vol 3A Tech Appx 2.3 Revised Drawing
12/10/2017 11:32:04 Supplementary Note Impact of Proposed Development on Regent's Park Revised Drawing
12/10/2017 11:31:51 A6 Revised Air Quality Assessment Rev B Revised Drawing
12/10/2017 11:31:41 D4 ES Vol 3A Tech Appx 2.3 Comments on Revised FRA 031017 Revised Drawing
12/10/2017 11:30:48 A10 Revised Construction Management Plan Rev 4 - 041017 Revised Drawing
12/10/2017 11:29:59 A21 Sus Design & Construction Statement Addendum Revised Drawing
12/10/2017 11:29:41 D4 ES Vol 3A Tech Appx 2.3 Revised Flood Risk Assessment and Drainage Strategy Revised Drawing
12/10/2017 11:29:29 D5 ES Vol 3B Addendum to Transport Assessment LARGE FILE Revised Drawing
12/10/2017 11:29:17 D4 ES Vol 3A Tech Appx 10.4 Revised solar glare assessment LARGE FILE Revised Drawing
12/10/2017 11:29:07 A15 Addendum to Noise and Vibration Impact Assessment Final Revised Drawing
12/10/2017 11:22:19 Design Development Notes for Revisions 171011 Revised Drawing
12/10/2017 11:19:53 BA Block A Revised elevations 140 to 143 Revised Drawing
12/10/2017 11:19:44 BA Revised Drawing register-Block A Revised Drawing
12/10/2017 11:19:27 BA Block A Revised sections 151 to 154 Revised Drawing
12/10/2017 11:19:18 BA Block A Revised ground floor plan 13508-A-A1_2-L00-100 Revised Drawing
12/10/2017 11:15:29 BPFS PFS Revised 170930-1605 Issue Sheet Revised Drawing
12/10/2017 11:15:21 BPFS PFS Revised Accommodation Schedule NIA Revised Drawing
12/10/2017 11:15:12 BPFS PFS Bay Studies Revised Drawing
12/10/2017 11:14:57 BPFS PFS Revised elevations first phase 301 to 304 Revised Drawing
12/10/2017 11:14:48 BPFS PFS Revised site and plans first phase 010 011 100 101 Revised Drawing
12/10/2017 11:14:38 BPFS PFS Revised sections 200 to 205 Revised Drawing
12/10/2017 11:14:28 BPFS PFS Revised plans final phase 010 to 012 and 099 to 106 Revised Drawing
12/10/2017 11:14:16 BPFS PFS Revised elevations final phase 300 to 304 Revised Drawing
12/10/2017 10:56:36 BM Masterplan Revised 7th floor 1095_00_07_107_P3 Revised Drawing
12/10/2017 10:56:26 BM Masterplan Revised 6th floor 1095_00_07_106_P3 Revised Drawing
12/10/2017 10:56:17 BM Masterplan Revised 5th floor 1095_00_07_105_P3 Revised Drawing
12/10/2017 10:56:08 BM Masterplan Revised 4th floor 1095_00_07_104_P3 Revised Drawing
12/10/2017 10:55:59 BM Masterplan Revised 3rd floor 1095_00_07_103_P3 Revised Drawing
12/10/2017 10:35:53 BM Masterplan Revised 2nd floor 1095_00_07_102_P3 Revised Drawing
12/10/2017 10:35:42 BM Masterplan Revised 1st floor 1095_00_07_101_P3 Revised Drawing
12/10/2017 10:35:31 BM Masterplan Revised lower ground Chalk Farm Road Level 1095_00_07_099_P3 Revised Drawing
12/10/2017 10:35:18 BM Masterplan Revised ground floor Oval Road Level 1095_00_07_100_P3 Revised Drawing
12/10/2017 10:35:09 BM Masterplan Revised 14th floor 1095_00_07_114_P3 Revised Drawing
12/10/2017 10:35:00 BM Masterplan Revised 13th floor 1095_00_07_113_P3 Revised Drawing
12/10/2017 10:34:48 BM Masterplan Revised 12th floor 1095_00_07_112_P3 Revised Drawing
12/10/2017 10:34:39 BM Masterplan Revised 11th floor 1095_00_07_111_P3 Revised Drawing
12/10/2017 10:34:30 BM Masterplan Revised 10thfloor 1095_00_07_110_P3 Revised Drawing
12/10/2017 10:34:21 BM Masterplan Revised 9th floor 1095_00_07_109_P3 Revised Drawing
12/10/2017 10:34:06 BM Masterplan Revised 8th floor 1095_00_07_108_P3 Revised Drawing
12/10/2017 10:33:33 BB Block B Revised Issue Register 171011_1095_CGY_Issue Register Revised Drawing
12/10/2017 10:33:24 BB Block B Revised plans 099 100 101 107 108 Revised Drawing
12/10/2017 10:33:15 BB Block B Revised elevations 201 to 204 Revised Drawing
12/10/2017 10:33:06 BB Block B Revised Bay studies 402 405 Revised Drawing
12/10/2017 10:22:41 BL Landscape Addendum to Design & Access Statement Low Res Revised Drawing
12/10/2017 10:22:25 BL Landscape Revised general arrangement P10606-00-001-101 Revised Drawing
12/10/2017 10:22:12 BL Landscape Revised Overall Masterplan P10606-00-001-100 Revised Drawing
12/10/2017 10:21:55 BL Landscape Addendum to Design & Access Statement High Res LARGE file Revised Drawing
12/10/2017 10:12:16 BF Block F Revised elevations 200 to 203 Revised Drawing
12/10/2017 10:12:09 BF Block F revised bay studies 401 404 406 Revised Drawing
12/10/2017 10:12:02 BF Block F Revised sections 300 302 303 Revised Drawing
12/10/2017 10:11:55 BF Block F Revised plans 100 to 109 Revised Drawing
12/10/2017 10:08:03 BE2 Block E2 Revised plans 100 to 105 Revised Drawing
12/10/2017 10:07:57 BE2 Block E2 Revised elevations 200 to 203 Revised Drawing
12/10/2017 10:07:50 BE2 Block E2 Revised bay studies 400 to 403 Revised Drawing
12/10/2017 10:07:44 BE2 Block E2 Unit types 500 to 502 Revised Drawing
12/10/2017 10:07:37 BE2 Block E2 Revised sections 300 301 Revised Drawing
12/10/2017 10:00:31 BE1 Block E1 Revised gnd floor 13508-A-E1-L00-100 Revised Drawing
12/10/2017 10:00:25 BE1 Block E1 Revised elevations 144 145 Revised Drawing
12/10/2017 10:00:20 BE1 Block E1 Revised Drawing register Revised Drawing
12/10/2017 10:00:15 BE1 Block E1 Revised sections 155 156 Revised Drawing
12/10/2017 09:56:49 BD Block D Revised sections 300 301 Revised Drawing
12/10/2017 09:56:43 BD Block D Revised plans 100 to 105 Revised Drawing
12/10/2017 09:56:36 BD Block D Revised elevations 200 to 203 Revised Drawing
12/10/2017 09:56:30 BD Block D Revised Bay Studies 400 to 402 Revised Drawing
12/10/2017 09:56:17 BD Block D Unit types 500 501 Revised Drawing
12/10/2017 09:51:47 BC Block C Bay studies Revised Drawing
12/10/2017 09:51:41 BC Block C Revised sections Revised Drawing
12/10/2017 09:51:33 BC Block C Revised plans Revised Drawing
12/10/2017 09:51:22 BC Block C Revised elevations Revised Drawing
21/09/2017 10:58:48 Further Revised Basement Impact Assessment Version 04 Revised Drawing
14/09/2017 18:11:15 Response 87 - One Housing Group Response (Redacted) Consultation Response
14/09/2017 17:55:47 Response 86 Consultation Response
13/09/2017 09:54:29 Revised Statement of Community Involvement Revised Drawing
12/09/2017 11:54:27 Response 85 Consultation Response
11/09/2017 19:43:33 Response 84 (Redacted) Consultation Response
11/09/2017 19:25:01 1x response (Redacted) Consultation Response
06/09/2017 09:24:42 Camden Goods Yard Working Group Response Consultation Response
06/09/2017 09:21:00 Regents Canal Conservation Area Advisory Committee Response Consultation Response
05/09/2017 18:03:32 Response 82 (Redacted) Consultation Response
04/09/2017 08:19:21 Response 81 (Redacted) Consultation Response
30/08/2017 14:59:18 D4 ES Vol 3A Tech 10.1 Additional appendix Daylighting Scenarios Neighbouring window maps Supporting Documents
30/08/2017 14:10:38 Response 80 (Redacted) Consultation Response
30/08/2017 14:07:46 Response 78 (Redacted) Consultation Response
06/07/2017 03:16:17 A1 Site Plan.pdf OS Extract
06/07/2017 03:16:18 A1 LocationPlan_included_in_SiteandOtherPlans.pdf M3 Document
06/07/2017 03:16:19 A1 Application Form (No Personal Data) Application Form
07/07/2017 09:01:31 A9 Basement Impact Assessment Part 2 of 3 Supporting Documents
07/07/2017 09:01:55 A9 Basement Impact Assessment Part 3 of 3 Supporting Documents
07/07/2017 09:02:14 A10 Construction Management Plan LBC Pro Forma Supporting Documents
07/07/2017 09:02:27 A11 Construction Management Plan Supporting Documents
07/07/2017 09:02:39 A12 Economic and Regeneration Impact Statement Supporting Documents
07/07/2017 09:02:52 A13 Framework Travel Plan Part 1 of 2 Supporting Documents
07/07/2017 09:03:00 A13 Framework Travel Plan Part 2 of 2 Supporting Documents
07/07/2017 09:03:07 A14 Health Impact Assessment Supporting Documents
07/07/2017 09:03:13 A15 Noise and Vibration Impact Assessment Supporting Documents
07/07/2017 09:03:21 A16 Pre-Development Arboricultural Survey Supporting Documents
07/07/2017 09:03:28 A17 Preliminary Bat Roost Assessment Supporting Documents
07/07/2017 09:03:35 A18 Preliminary Ecological Assessment Supporting Documents
07/07/2017 09:05:09 A19 Servicing Management Plan Part 1 of 1 Supporting Documents
07/07/2017 09:05:16 A19 Servicing Management Plan Part 2 of 2 Supporting Documents
07/07/2017 09:05:25 A20 Statement of Community Involvement Part 1 of 3 Supporting Documents
07/07/2017 09:05:35 A20 Statement of Community Involvement Part 2 of 3 Supporting Documents
07/07/2017 09:05:44 A20 Statement of Community Involvement Part 3 of 3 Supporting Documents
07/07/2017 09:05:53 A21 Sus Design & Constr Vol 1 - Main Report Supporting Documents
07/07/2017 09:06:08 A21 Sus Design & Constr Vol 2 Energy Statement EST48232 Issue 2 - Part 1 of 2 Supporting Documents
07/07/2017 09:06:16 A21 Sus Design & Constr Vol 2 Energy Statement EST48232 Issue 2 - Part 2 of 2 Supporting Documents
07/07/2017 09:06:25 A21 Sus Design & Constr Vol 3 - BREEAM Pre-Assessment Supporting Documents
07/07/2017 09:06:31 A21 Sus Design & Constr Vol 4 - Thermal Comfort Supporting Documents
07/07/2017 09:06:38 A2 CIL Form 04 07 2017 Supporting Documents
07/07/2017 09:06:45 A4 Cover Letter Supporting Documents
07/07/2017 09:06:54 A5 Affordable Housing Statement Supporting Documents
07/07/2017 09:07:04 A6 Air Quality Assessment Supporting Documents
07/07/2017 09:07:12 A7 Arboricultural Impact Assessment Supporting Documents
07/07/2017 09:07:20 A8 Archaeological Desk Based Assessment Part 1 of 2 Supporting Documents
07/07/2017 09:07:27 A8 Archaeological Desk Based Assessment Part 2 of 2 Supporting Documents
07/07/2017 09:07:34 A9 Basement Impact Assessment Audit Form Supporting Documents
07/07/2017 09:07:41 A9 Basement Impact Assessment Part 1 of 3 Supporting Documents
07/07/2017 12:06:27 BB Block B Elevations 200 to 203 Proposed Drawing
07/07/2017 12:06:42 BB Block B Plans 99 to 108 Proposed Drawing
07/07/2017 12:06:59 BB Block B residential layouts 500 to 503 Proposed Drawing
07/07/2017 12:07:06 BB Block B Sections 204 to 207 Proposed Drawing
07/07/2017 12:07:20 BC Block C bay studies 400 to 402 Proposed Drawing
07/07/2017 12:07:31 BC Block C north east north west elevations 203 204 Proposed Drawing
07/07/2017 12:07:46 BC Block C plans 100 to 110 Proposed Drawing
07/07/2017 12:07:58 BC Block C residential layouts 1095_03_07_500 Proposed Drawing
07/07/2017 12:08:05 BC Block C sections 300 to 302 Proposed Drawing
07/07/2017 12:08:18 BC Block C south east south west elevations 201 202 Proposed Drawing
07/07/2017 12:08:31 BD Block D bay studies 400 to 402 Proposed Drawing
07/07/2017 12:08:38 BD Block D elevations 200 to 203 and sections 300 301 Proposed Drawing
07/07/2017 12:20:16 BD Block D plans and resi layouts Proposed Drawing
07/07/2017 12:20:25 BE1 Block E1 elevations sections Proposed Drawing
07/07/2017 12:20:32 BE1 Block E1 plans gnd to roof Proposed Drawing
07/07/2017 12:20:42 BE2 Block E2 bay studies 400 to 403 Proposed Drawing
07/07/2017 12:20:51 BE2 Block E2 elevations 200 to 203 and sections 300 301 Proposed Drawing
07/07/2017 12:21:03 BE2 Block E2 plans and resi layouts Proposed Drawing
07/07/2017 12:21:17 BF Block F bay studies 400 to 407 Proposed Drawing
07/07/2017 12:21:28 BF Block F elevations 200 to 203 sections 300 to 302 Proposed Drawing
07/07/2017 12:21:40 BF Block F plans 100 to 109 resi layouts 500 501 Proposed Drawing
07/07/2017 12:21:57 BPFS PFS demolition 50 51 Existing Drawing
07/07/2017 12:22:12 BPFS PFS Drawing Release Sheet 1605-IS-Planning Other
07/07/2017 12:22:20 BPFS PFS existing drawings Existing Drawing
07/07/2017 12:22:31 BPFS PFS plans 2nd to roof Proposed Drawing
07/07/2017 12:22:40 BPFS PFS plans final phase basement to 1st Proposed Drawing
07/07/2017 12:22:52 BPFS PFS plans first phase gnd to 1st Proposed Drawing
07/07/2017 12:23:02 BPFS PFS sections elevations final phase Proposed Drawing
07/07/2017 12:23:21 BPFS PFS sections elevations first phase Proposed Drawing
07/07/2017 12:24:47 B Drawings AAM Issue Sheet 1095_CGY_Issue Register Other
07/07/2017 12:25:16 B Drawings Area Schedule Other
07/07/2017 12:25:27 BA Block A 13508-PCO-Drawing register Other
07/07/2017 12:25:41 BA Block A plans Proposed Drawing
07/07/2017 12:26:18 BA Block A sections and elevations Proposed Drawing
07/07/2017 12:26:56 BB Block B Bay studies 400 to 405 Proposed Drawing
07/07/2017 12:30:37 BM Masterplan Demolition plans 1095_00_07_002 Existing Drawing
07/07/2017 12:30:46 BM Masterplan Existing Demolition elevations 1095_00_07_003 Existing Drawing
07/07/2017 12:30:53 BM Masterplan ground floor 1095_00_07_100 Proposed Drawing
07/07/2017 12:31:03 BM Masterplan lower car parking (basement) 1095_00_07_098 Proposed Drawing
07/07/2017 12:31:17 BM Masterplan lower ground (Chalk Farm Road level) 1095_00_07_099 Proposed Drawing
07/07/2017 12:31:27 BM Masterplan lower ground floor 4 plans 115 to 118 Proposed Drawing
07/07/2017 12:31:45 BM Masterplan sections AA BB 1095_00_07_300 Proposed Drawing
07/07/2017 12:31:59 BM Masterplan sections DD EE 1095_00_07_301 Proposed Drawing
07/07/2017 12:32:15 BM Masterplan sections FF GG 1095_00_07_302 Proposed Drawing
07/07/2017 12:32:29 BM Masterplan sections HH 1095_00_07_303 Proposed Drawing
07/07/2017 12:32:41 BM Masterplan site location 1095_00_07_001 OS Extract
07/07/2017 12:33:15 BM AAM Drawing Issue Sheet 1095_CGY_Issue Register_170706 Other
07/07/2017 12:33:27 BM Camden Yard plans and elevations 1095_00_07_200 Proposed Drawing
07/07/2017 12:33:37 BM Masterplan 1st floor 1095_00_07_101 Proposed Drawing
07/07/2017 12:33:55 BM Masterplan 2nd floor 1095_00_07_102 Proposed Drawing
07/07/2017 12:34:07 BM Masterplan 3rd floor 1095_00_07_103 Proposed Drawing
07/07/2017 12:34:17 BM Masterplan 4th floor 1095_00_07_104 Proposed Drawing
07/07/2017 12:34:27 BM Masterplan 5th floor 1095_00_07_105 Proposed Drawing
07/07/2017 12:34:39 BM Masterplan 6th floor 1095_00_07_106 Proposed Drawing
07/07/2017 12:34:50 BM Masterplan 7th floor 1095_00_07_107 Proposed Drawing
07/07/2017 12:35:00 BM Masterplan 8th floor 1095_00_07_108 Proposed Drawing
07/07/2017 12:35:09 BM Masterplan 9th floor 1095_00_07_109 Proposed Drawing
07/07/2017 12:35:20 BM Masterplan 10th floor 1095_00_07_110 Proposed Drawing
07/07/2017 12:35:32 BM Masterplan 11th floor 1095_00_07_111 Proposed Drawing
07/07/2017 12:35:42 BM Masterplan 12th floor 1095_00_07_112 Proposed Drawing
07/07/2017 12:35:52 BM Masterplan 13th floor 1095_00_07_113 Proposed Drawing
07/07/2017 12:36:02 BM Masterplan 14th floor 1095_00_07_114 Proposed Drawing
07/07/2017 13:37:15 A3 Planning Statement Supporting Documents
07/07/2017 13:42:13 D0 Environmental Statement Non technical Summary (high res) VERY LARGE FILE Supporting Documents
07/07/2017 13:42:28 D0 Environmental Statement Non technical Summary (low res) Supporting Documents
07/07/2017 13:43:29 D3 ES Vol 2B Built Heritage Appdx 2 Statement of Significance Listed Buildings part 2 of 3 Supporting Documents
07/07/2017 13:43:39 D3 ES Vol 2B Built Heritage with Appendix 1 Heritage Asset plans part 1 of 3 Supporting Documents
07/07/2017 13:43:51 D3 ES Vol 2B Built Heritage Appdices 3 to 7 part 3 of 3 Supporting Documents
07/07/2017 13:44:20 D2 ES Vol2A TVIA Ch 6 Views 13 to 16 Part5 of 15 Supporting Documents
07/07/2017 13:44:28 D2 ES Vol2A TVIA Ch 6 Views 9 to 12 Part4 of 15 Supporting Documents
07/07/2017 13:44:37 D2 ES Vol2A TVIA Ch 6 Views 5 to 8 Part3 of 15 Supporting Documents
07/07/2017 13:44:44 D2 ES Vol2A TVIA Ch 6 Views 1 to 4 Part2 of 15 Supporting Documents
07/07/2017 13:44:51 D2 ES Vol2A TVIA Ch 6 to end Part12 of 15 Supporting Documents
07/07/2017 13:45:22 D2 ES Vol2A TVIA Ch 1 to 6 Part1 of 15 Supporting Documents
07/07/2017 13:45:34 D2 ES Vol2A TVIA complete VERY LARGE FILE Supporting Documents
07/07/2017 13:46:08 D2 ES Vol2A TVIA Ch 7 Views A11 to END Part15 of 15 Supporting Documents
07/07/2017 13:46:16 D2 ES Vol2A TVIA Ch 7 Views A7 to A10 Part14 of 15 Supporting Documents
07/07/2017 13:46:24 D2 ES Vol2A TVIA Ch 7 Views A1 to A6 Part13 of 15 Supporting Documents
07/07/2017 13:46:32 D2 ES Vol2A TVIA Ch 6 Views 32 to 37 Part11 of 15 Supporting Documents
07/07/2017 13:46:40 D2 ES Vol2A TVIA Ch 6 Views 29 to 31 Part10 of 15 Supporting Documents
07/07/2017 13:46:52 D2 ES Vol2A TVIA Ch 6 Views 25 to 28 Part9 of 15 Supporting Documents
07/07/2017 13:46:59 D2 ES Vol2A TVIA Ch 6 Views 24 Part8 of 15 Supporting Documents
07/07/2017 13:47:08 D2 ES Vol2A TVIA Ch 6 Views 21 to 23 Part7 of 15 Supporting Documents
07/07/2017 13:47:14 D2 ES Vol2A TVIA Ch 6 Views 17 to 20 Part6 of 15 Supporting Documents
07/07/2017 13:59:59 C DAS Ch6 Design Statement Block B Design and Access Statement
07/07/2017 14:00:16 C DAS Ch6 Design Statement Block C Design and Access Statement
07/07/2017 14:00:31 C DAS Ch6 Design Statement Block D Design and Access Statement
07/07/2017 14:00:51 C DAS Ch6 Design Statement Block E1 Design and Access Statement
07/07/2017 14:01:01 C DAS Ch6 Design Statement Block E2 Design and Access Statement
07/07/2017 14:01:16 C DAS Ch6 Design Statement Block F Design and Access Statement
07/07/2017 14:01:35 C DAS Ch6 Design Statement PFS LARGE FILE Design and Access Statement
07/07/2017 14:02:02 C DAS Ch7 Public Realm and Landscape Design and Access Statement
07/07/2017 14:02:29 C DAS Ch9 Appendix A FutureProofing Design and Access Statement
07/07/2017 14:02:42 C DAS Ch9 Appendix B Lighting WhiteCode LARGE FILE Design and Access Statement
07/07/2017 14:03:04 C DAS Ch9 Appendix E Fire Strategy Design and Access Statement
07/07/2017 14:03:13 C DAS Ch9 Appendix F Statement of Public consultation To End LARGE FILE *Superseded* Design and Access Statement
07/07/2017 14:03:32 C DAS Ch1-3 Intro Vision Site context Design and Access Statement
07/07/2017 14:03:53 C DAS Ch4 Design Evolution Design and Access Statement
07/07/2017 14:04:13 C DAS Ch5 Proposed Scheme Part 1 of 4 Uses Design and Access Statement
07/07/2017 14:04:27 C DAS Ch5 Proposed Scheme Part 2 of 4 Layout LARGE FILE Design and Access Statement
07/07/2017 14:04:43 C DAS Ch5 Proposed Scheme Part 3 of 4 Connectivity Public Spaces Design and Access Statement
07/07/2017 14:05:26 C DAS Ch5 Proposed Scheme Part 4 of 4 Massing & Scale Site Wide Strategies Safer Places Design and Access Statement
07/07/2017 14:05:36 C DAS Ch6 Design Statement Block A Design and Access Statement
07/07/2017 14:37:06 D5 ES Vol 3B Trans Assess Traffic Survey Data Part 3 of 9 Supporting Documents
07/07/2017 14:37:20 D5 ES Vol 3B Transport Assessment Appdx H I Site Layout Road Safety Audit Part 7 of 9 Supporting Documents
07/07/2017 14:37:37 D5 ES Vol 3B Transport Assessment Appdx J K TRICS Data Census Data Part 8 of 9 Supporting Documents
07/07/2017 14:37:50 D5 ES Vol 3B Transport Assessment Appdx L M LinSIG Results POERS Audit Part 9 of 9 Supporting Documents
07/07/2017 14:38:02 D5 ES Vol 3B Trans Assess Appdx D to G Boundary Traffic Flow Injury Data WebCAT PTAL Part 6 of 9 Supporting Documents
07/07/2017 14:38:20 D5 ES Vol 3B Trans Assess Appendix B parking technical notes Part 4 of 9 Supporting Documents
07/07/2017 14:38:48 D5 ES Vol 3B Trans Assess Appendix C TfL Advice Letters Part 5 of 9 Supporting Documents
07/07/2017 14:39:03 D5 ES Vol 3B Trans Assess Chs 1 to 10 and Figures part 1 of 9 Supporting Documents
07/07/2017 14:39:38 D5 ES Vol 3B Trans Assess Drawings and Appendix A Scoping note Part 2 of 9 Supporting Documents
07/07/2017 14:41:49 D4 ES Vol 3A Tech Appx 10.4 Solar Glare Assessment part 3 of 3 Supporting Documents
07/07/2017 14:42:06 D4 ES Vol 3A Tech Appx 10.5 Light Pollution Assessment Supporting Documents
07/07/2017 14:42:20 D4 ES Vol 3A Tech Appx 10.6 Internal daylight sunlight assessment part 1 of 8 Supporting Documents
07/07/2017 14:42:40 D4 ES Vol 3A Tech Appx 10.6 Internal daylight sunlight assessment part 2 of 8 Supporting Documents
07/07/2017 14:43:03 D4 ES Vol 3A Tech Appx 10.6 Internal daylight sunlight assessment part 3 of 8 Supporting Documents
07/07/2017 14:43:19 D4 ES Vol 3A Tech Appx 10.6 Internal daylight sunlight assessment part 4 of 8 Supporting Documents
07/07/2017 14:43:35 D4 ES Vol 3A Tech Appx 10.6 Internal daylight sunlight assessment part 5 of 8 Supporting Documents
07/07/2017 14:43:50 D4 ES Vol 3A Tech Appx 10.6 Internal daylight sunlight assessment part 6 of 8 Supporting Documents
07/07/2017 14:44:07 D4 ES Vol 3A Tech Appx 10.6 Internal daylight sunlight assessment part 7 of 8 Supporting Documents
07/07/2017 14:44:21 D4 ES Vol 3A Tech Appx 10.6 Internal daylight sunlight assessment part 8 of 8 Supporting Documents
07/07/2017 14:44:37 D4 ES Vol 3A Tech Appx 11.1 Pedestrian Level Wind Microclimate Assessment Supporting Documents
07/07/2017 14:44:49 D4 ES Vol 3A Tech Appx 1.1-2.1 IEMA Quality Scoping Opinion Part 1 of 3 Supporting Documents
07/07/2017 14:45:04 D4 ES Vol 3A Tech Appx 2.1 Scoping Opinion App 4 Prelim Risk Assess App 5 Viewpoints Part 3 of 3 VERY LARGE FILE Supporting Documents
07/07/2017 14:45:43 D4 ES Vol 3A Tech Appx 2.1 Scoping Opinion Archaeology Desk Assessment Part 2 of 3 LARGE FILE Supporting Documents
07/07/2017 14:46:16 D4 ES Vol 3A Tech Appx 2.3 Flood Risk assess and Surface Water Drainage Strategy LARGE FILE Supporting Documents
07/07/2017 14:46:40 D4 ES Vol 3A Tech Appx 9.1 Acoustic Term 9.2 Baseline Noise and Vibration Supporting Documents
07/07/2017 14:46:54 D4 ES Vol 3A Tech Appx 9.3 to 10.1 Traffic Flow Amenity Space Glazing Mitigation Scenarios Supporting Documents
07/07/2017 14:47:06 D4 ES Vol 3A Tech Appx 10.2 Daylight Sunlight Assessment Supporting Documents
07/07/2017 14:47:18 D4 ES Vol 3A Tech Appx 10.3 Overshadowing Assessment LARGE FILE Supporting Documents
07/07/2017 14:47:42 D4 ES Vol 3A Tech Appx 10.4 Solar Glare Assessment part 1 of 3 Supporting Documents
07/07/2017 14:47:58 D4 ES Vol 3A Tech Appx 10.4 Solar Glare Assessment part 2 of 3 Supporting Documents
07/07/2017 14:49:44 D1 ES Main Report Ch 5 to 10 Demo Consttuct Socio Economics Transport Air Quality Noise Daylight part 3 of 4 Supporting Documents
07/07/2017 14:50:01 D1 ES Main Report Ch 11 to end Wind Microclimate Cumulative Summary of Residuals part 4 of 4 Supporting Documents
07/07/2017 14:50:16 D1 ES Main Report Ch 1 to 3 Intro Methodology Alternatives part 1 of 4 Supporting Documents
07/07/2017 14:50:31 D1 ES Main Report Ch 4 Proposed Development part 2 of 4 Supporting Documents
11/07/2017 14:26:07 Responses #1a/1b Consultation Response
13/07/2017 12:53:07 BL Landscape Hardworks plan P10606-00-001-102 Proposed Drawing
13/07/2017 12:53:21 BL Landscape sections 200 to 203 Proposed Drawing
13/07/2017 12:53:34 BL Landscape Softworks P10606-00-001-103 Proposed Drawing
13/07/2017 12:53:47 BL Landscape general arrangement P10606-00-001-101 Proposed Drawing
13/07/2017 12:54:24 A9a BIA extracts from LORP0004 FRA showing TWU assets Supporting Documents
17/07/2017 13:12:37 aA0 Paper Copy of application is in Primrose Hill Community Library - details attached Other
19/07/2017 14:13:07 A22 Contextual Daylight and Density Research Supporting Documents
19/07/2017 15:57:31 Response #1 Consultation Response
20/07/2017 15:52:52 Pre-application advice Other
20/07/2017 15:54:13 CGY: Camden Design Review Panel report from 1st session Other
20/07/2017 15:54:55 CGY: Camden Design Review Panel report from 2nd session Other
20/07/2017 15:55:48 CGY: Camden Design Review Panel report from 3rd session Other
26/07/2017 11:26:49 C DAS Ch9 Appendix B Signage Strategy Design and Access Statement
26/07/2017 11:29:30 C DAS Ch9 Appendix D Competition Brief for External Lift Design and Access Statement
26/07/2017 14:50:41 Response #2 (Redacted) Consultation Response
26/07/2017 15:19:12 Thames Water comments Consultation Response
26/07/2017 17:30:09 Response #3 (Redacted) Consultation Response
27/07/2017 10:53:28 Historic England GLAAS advice. (Redacted) Consultation Response
27/07/2017 15:53:47 Environment Agency comments Consultation Response
31/07/2017 12:36:59 Canal & River Trust Response Consultation Response
01/08/2017 13:25:14 Response #4 (Redacted) Consultation Response
01/08/2017 13:34:34 Response #5 (Redacted) Consultation Response
02/08/2017 13:54:57 Response #6 Consultation Response
04/08/2017 13:30:37 C DAS Ch9 Appendix F Statement of Public consultation To End LARGE FILE Design and Access Statement
07/08/2017 12:12:34 C DAS Ch8 Access Statement Design and Access Statement
08/08/2017 14:28:13 Responses #7-11 Consultation Response
09/08/2017 15:16:55 Response #12 (Redacted) Consultation Response
10/08/2017 08:38:57 Response #13 (Redacted) Consultation Response
10/08/2017 10:30:06 Responses #14-21 Consultation Response
11/08/2017 13:10:58 Responses #22-24 Consultation Response
14/08/2017 10:45:22 D4 ES Vol 3A Tech Appx 10.6 Overshadowing assessment part 8a of 8 Supporting Documents
15/08/2017 08:14:26 Historic England Response (redacted) Consultation Response
15/08/2017 08:32:34 1 x Response - HS2 (Redacted) Consultation Response
15/08/2017 14:55:23 Revised Basement Impact Assessment 2017_Version 03 (Issued) Revised Drawing
15/08/2017 14:56:10 Geo-environmental Appraisal. C3821 - June 2010 Supporting Documents
15/08/2017 17:23:11 Natural England consultation response Consultation Response
15/08/2017 17:23:32 Camden and Islington Public Health response Consultation Response
17/08/2017 11:16:09 Responses #25-33 (Redacted) Consultation Response
17/08/2017 11:17:32 Primrose Hill CAAC response (Redacted) Consultation Response
17/08/2017 11:18:24 Cllr Pat Callaghan response (Redacted) Consultation Response
17/08/2017 11:18:54 Camden Cycling Campaign response (Redacted) Consultation Response
17/08/2017 13:18:00 Responses #34-74 Consultation Response
17/08/2017 15:01:08 Responses #75-76 (Redacted) Consultation Response
30/08/2017 11:13:33 Camden Railway Heritage Trust Response Consultation Response
30/08/2017 12:03:12 1 x Response - Network Rail Consultation Response

Copyright Warning

Plans, drawings and material submitted to the council are protected by the copyright acts (section 47, 1988 act). You may only use material which is downloaded and/or printed for consultation purposes, to compare current applications with previous schemes and to check whether developments have been completed in accordance with approved plans. Further copies must not be made without the prior permission of the copyright owner.