From: Leon Gadsdon [leon@enmassedesign.co.uk]
Sent: 19 May 2016 16:33
To: Anna P Fleming; 'BPR
Architects'
Cc: 'Iain Brewester'; 'Fardad
Ghaffari'; 'Colin Hayward'; 'Cameron Ogle'; 'Dunedin Construction'; 'Brett
Manning'; 'Rosie Seaman'
Subject: RE: 69 Highgate High Street -
CfSH Information
Follow Up Flag: Follow up
Flag Status: Flagged
Hi Anna
I can confirm that the
drying room will have continuous extract of minimum 8L/S which is equal to Part
F intermittent extract.
Thanks
Leon
Gadsdon
BEng [Hons] CEng MCIBSE
Director
En Masse Design Limited
Building Services Consulting Engineers
Thorncroft Manor
Thorncroft Drive
Leatherhead
Surrey KT22 8JB
T: 01372 224 745
M: 07766 078 318
E: leon@enmassedesign.co.uk
W: www.enmassedesign.co.uk
Company Registration No: 4307290
The information contained within this e-mail is confidential and may be
privileged. It is intended for the addressee only, if you have received
the e-mail in error please inform the sender and delete this e-mail
immediately. The contents of this e-mail must not be disclosed or copied without
the senders consent.
From: Anna P Fleming [mailto:anna.fleming@synconsult.co.uk]
Sent: Thursday, May 19, 2016 3:37 PM
To: BPR Architects
Cc: Iain Brewester; Leon Gadsdon; Fardad Ghaffari; Colin Hayward; Cameron
Ogle; Dunedin Construction; Brett Manning; Rosie Seaman
Subject: RE: 69 Highgate High Street - CfSH Information
Hi Rosie,
I have gone through all the
evidence sent over and have updated the HitList.
Please see below comments too.
Please give me a call to run
through any queries.
Kind regards
Anna
Anna Fleming | Associate Director | Synergy Consulting
Engineers Ltd (Reg No. 6383504) 1 Canal Side Studios | 8-14 St Pancras Way
| London NW1 0QG Tel: 020 7529 8954 | Mob: 07803 125053 | Fax:
020 7388 9312 | Email: anna.fleming@synconsult.co.uk
From: BPR Architects [mailto:info@birdsportchmouthrussum.com]
Sent: 16 May 2016 18:37
To: Anna P Fleming
Cc: Iain Brewester; Leon Gadsdon; Fardad Ghaffari; Colin Hayward;
Cameron Ogle; Dunedin Construction; Brett Manning; Rosie Seaman
Subject: 69 Highgate High Street - CfSH Information
Dear Anna,
Please find below
a dropbox link containing BPR information for the CfSH Hitlist:
We believe
that this package completes the entire body of information you require from BPR
Architects. This folder supersedes any information we sent you
previously.
For sections that
need locations indicated on plan I have combined the information on drawings
'HG.CSH.001-004'.
The information
within the folder includes:
Ene 1, Ene 2
& Ene 7
SAP Calculations
SYN - The SAP
calculations undertaken are Part L 2013 which you need for Building Control. We
need a copy of the SAP Calculation run under Part L 2010
Ene 3 每 Energy
Display Devices
Location &
Specification of Gas & Electricity Meters shown on HG.CSH.001
Confirmation
letter from client
SYN - Complete
Ene 4 - Drying
Space
Specification,
location & air change rate shown on HG.CSH.003
ENE 4 Supplement
checklist completed
Confirmation
letter from client
SYN - Air
change rate shown but the guidance states a minimum of 30l/s is required via
intermittent fan. The flow rate can be a lot less as continuous but need additional note re that 8 l/s continuous
is equal to Part F intermittent
Ene 5 每 White
Goods
Locations shown
on HG.CSH.003-004
2005: White Goods
Schedule with energy ratings
Confirmation
letter from client
SYN - Complete
Ene 6 每
External Lighting
Locations shown
on HG.CSH.001-002
SH.2006:
Electrical Fitting Specification: Luminaires
SYN - Can't see
the fittings on the drawings provided! Also need the efficacy of the fittings
to be added to the table. These fitting need to be above 40 lumens per Watt/m.
Fitting need to be font entrance, staircase and any lighting on the terrace.
Ene 9 每 Home
Office
HG.CSH.004 marked
with location, required electrics & openable window
Daylight factor to
be suppled by Synergy
SYN - Can you
please add a note onto the drawing with the openable casement size. Joseph has
been in touch with what he needs for daylighting calculations which should be
completed tomorrow / Monday.
Wat 1 每 int
Usage
Sanitary-ware
& white goods shown in 2004: Sanitaryware Schedule confirming flow rate,
bath capacity and consumption
HG.CSH.003-004
show locations and relate back to the sanitary ware schedule
Requirement of ≒ 105l/p/day confirmed by Services
Engineer
Confirmation letter by client
SYN - Complete
Mat 1 - Materials
MAT 1 calculation
tool completed
Drawings with
specification
SYN - Can you
please provide the unique green guide codes for each element. Can I also have
the drawings referenced
Mat 2 每 Sourcing
Basic Building Elements
MAT 2 calculation tool
completed
Confirmation letter from
client
SYN - Complete
Mat 3 每 Sourcing
Finishing Elements
MAT 3 calculation tool
completed
Confirmation letter from
client
SYN - Complete
Was 1 每 Waste
Locations &
specification shown on HG.CSH.001 & 004 for Internal Storage
HG.EW.3030 for External
Storage
IDP Checklist
Table 5.1
SYN - Just need
either email of extract from Camden Website confirming the frequency of
collection and what is collected. We will be able to get an additional credit
for WAS 3 since there is a food waste scheme just need details of scheme (i.e.
extract from Camden's website)
Pol 1 每 GWP
POL 1 Checklist
Literature on products
confirming GWP
SYN - Complete
Pol 2 每 Nox
Boiler Specification
confirming class 5
SYN - Complete
Hea 2 -
Sound
Confirmation letter from
client
(We have the report if
required)
SYN -
Unfortunately the letter doesn't state the target set or the fact that testing
will be carried to confirm compliance. If the report covers both these elements
we can use instead of the letter
Hea
3 每 Private Space
Balcony area and
location show on HG.CSH.004
HEA 3 calculation
tool completed
SYN - Complete
Hea 4 每
Lifetime Homes
HEA 4 checklist
completed
SYN - Complete
Man 4 每
Security
CPDA letter
included
Confirmation letter from client
SYN - Complete
For some of the checklists
and calculator tools we have left the information regarding the 'Dwelling
reference', 'Issue Date' etc clear 每 please could you fill these in or let me
know what information we need to put in them.
We would be
grateful if you could confirm you have received all the information.
Kind regards,
Rosie Seaman
Birds Portchmouth Russum Architects Ltd.
Unit 11, Union Wharf
23 Wenlock Road
London N1 7SB
www.birdsportchmouthrussum.com
t: 020 7253 8205
This message has been sent on behalf of Birds Portchmouth Russum
Architects (BPR) and contains information intended for the
addressee(s). If you are not the intended recipient you are notified that
disclosing, copying, distributing or taking any action in reliance on the
contents of this information is strictly prohibited. If you have received
this e-mail in error, please notify BPR immediately by e-mail and delete
any copies made from your system.
From:
Anna P Fleming <anna.fleming@synconsult.co.uk>
Date: Thursday, 28 April 2016 11:24
To: BPR ARCHITECTS <info@birdsportchmouthrussum.com>
Cc: Iain Brewester <iain@westsidelondon.com>,
Jim grace <jim.grace@synconsult.co.uk>,
Leon Gadsdon <leon@enmassedesign.co.uk>
Subject: RE: 69, Highgate High Street - CfSH Fee Proposal
Dear Mike,
As discussed yesterday, please
find attached updated HitList detailing the information I require to complete
the Design Assessment.
I have also attached the
guidance and all the tools and checklists.
Please review and give me a call
to run through if you have any queries.
Kind regards
Anna
Anna Fleming | Associate Director | Synergy Consulting Engineers
Ltd (Reg No. 6383504) 1 Canal Side Studios | 8-14 St Pancras Way |
London NW1 0QG Tel: 020 7529 8954 | Mob: 07803 125053 |Fax: 020 7388 9312 |
Email: anna.fleming@synconsult.co.uk
From:
BPR Architects [mailto:info@birdsportchmouthrussum.com]
Sent: 26 April 2016 15:47
To: Anna P Fleming
Cc: Iain Brewester; James Grace; Leon Gadsdon
Subject: Re: 69, Highgate High Street - CfSH Fee Proposal
Dear Anna,
Many thanks 每 as discussed today our client, Iain Brewester, has
agreed to you preparing the Sustainability Design Assessment as a matter of
great urgency.
Please find below dropbox links to our drawings, design
proposals by Leon Gadsdon of En Masse, the SAPS Calculations
prepared by Mike Ovenden of Gecko, an Acoustic Report by Cole Jarman and a copy
of your original CFSH Planning submission.
BPR Tender Drawings issued 26 February 2016 (we will send a new
link later in the week to the revised tender issue : https://www.dropbox.com/sh/1bmzn5v51lga58c/AACXnngTz7iZOUHBcMQ94L5qa?dl=0
Drawings by En Masse, SAPS, Acoustic and CfSH documents : https://www.dropbox.com/sh/7r68r03neds2jwv/AAA7_qLqYOcVDmL7qkaVCvSza?dl=0
If you could get us your list of required information asap we will
respond asap.
Best wishes,
Mike Russum
Birds Portchmouth Russum Architects Ltd.
Unit 11, Union Wharf
23 Wenlock Road
London N1 7SB
www.birdsportchmouthrussum.com
t: 020 7253 8205
This message has been sent on behalf of Birds Portchmouth Russum
Architects (BPR) and contains information intended for the
addressee(s). If you are not the intended recipient you are notified that
disclosing, copying, distributing or taking any action in reliance on the
contents of this information is strictly prohibited. If you have received
this e-mail in error, please notify BPR immediately by e-mail and delete
any copies made from your system.
From: Anna P Fleming <anna.fleming@synconsult.co.uk>
Date: Wednesday, 20 April 2016 17:20
To: BPR ARCHITECTS <info@birdsportchmouthrussum.com>
Cc: Jim grace <jim.grace@synconsult.co.uk>
Subject: 69, Highgate High Street - CfSH Fee Proposal
Hi Mike,
Jim has asked me to send an email
over to you for carrying out the formal CfSH assessments for 69, Highgate High
Street.
I know from experience that you
will not achieve the Design Assessment before the 1st May even if we received
all the information / evidence tomorrow.
Timeline to complete
Email setting out all information
required - an hour
Need to register the site - half
an hour
On receipt of information (as long
as everything is complete and correct) - 1 day to complete and submit the
report
Stroma will then take 7 working
days to assess
They usually do not sign off the assessment
1st time round (they like their QA fees!) so need a couple of days to amend and
re-submit and then 2 to 3 for a response from Stroma.
Therefore the earliest would be
second week of May if you can get all evidence over to me this week!
Please give me a call if you wish
to discuss.
Kind regards
Anna
Anna Fleming | Associate Director | Synergy Consulting Engineers
Ltd (Reg No. 6383504) 1 Canal Side Studios | 8-14 St Pancras Way |
London NW1 0QG Tel: 020 7529 8954 | Mob: 07803 125053 |Fax: 020 7388 9312 |
Email: anna.fleming@synconsult.co.uk